fuselage bulkhead AD 47-50-02

Posted: Wed Nov 11, 2020 6:37 pm
by 8475
Hello everyone, I'll start by apologizing for revisiting a topic that has probably already been covered in detail in the forum.

I'm a new 140 owner and am going through my first annual inspection. My question involves the rear bulkhead reinforcement AD, 47-50-02. The Cessna service letter 46, which addresses this same topic, suggests that the vertical stabilizer be removed for the inspection. Is this actually necessary? Is there some other way to confirm if this fix has been applied to my plane? Appreciate the advice.
-dave

Re: fuselage bulkhead AD 47-50-02

Posted: Wed Nov 11, 2020 8:48 pm
by 6597
viewtopic.php?f=7&t=1231&p=8334#p8334

If the doubler is installed you should be able to see the top of it by looking into the hole where the lower elevator horn enters and seeing a sort of shelf.

Re: fuselage bulkhead AD 47-50-02

Posted: Wed Nov 11, 2020 11:49 pm
by 8475
David, thank you for the answer and for the link. That's perfect. Appreciate it.